DMK Contracting was engaged by Aaron George Builders to deliver the underground services for the Franklyn Park residential development on Towai Street, supporting a new 24-lot subdivision.

The team completed the installation of the development’s stormwater, wastewater and water infrastructure. Works included 150 mm and 100 mm PVC sewer mains, 150 mm PVC water mains, 63 mm PE pipework and 24 individual 25 mm service laterals.

DMK also installed 20 × 1050 mm manholes across the sewer and stormwater networks, along with 375 mm OD concrete stormwater pipe.

The project involved the coordinated delivery of the subdivision’s core three-waters infrastructure, providing the essential underground services required for the development of all 24 residential sites.



Partially backfilled excavation with a concrete manhole and plate compactor.

The Solution

  • Stormwater, wastewater and water infrastructure

  • 150 mm and 100 mm PVC sewer mains

  • 150 mm PVC water main

  • 63 mm PE pipework

  • 24 × 25 mm service laterals

  • 20 × 1050 mm sewer and stormwater manholes

  • 375 mm OD concrete stormwater pipe

Outcome

DMK delivered the underground three-waters infrastructure required to service the new 24-lot residential development, coordinating the installation of water, wastewater and stormwater networks across the site.

The works brought together multiple pipe systems, service laterals and manhole installations as part of a coordinated infrastructure package, providing the essential underground services required for the development of all 24 residential sites.

Project Gallery

Concrete manholes installed along a long excavated trench with standing water.
Partially backfilled excavation with a concrete manhole and plate compactor.
Worker beside a concrete manhole in a gravel-filled trench.
Services

Water Infrastructure

Wastewater Infrastructure

Stormwater Infrastructure

Pipeline Renewals & Maintenance

PE Pipe Installation & Welding

Contact

PH 027 202 5142

E info@dmkcontracting.co.nz

F @DMKcontracting

© 2026 DMK Contracting All rights reserved.